Combined cycle natural gas based grid connected power plant at Jegurupadu, India
Industrial & Commercial · Natural Gas Electricity Generation · India
CORSIA-approved programmeDimension breakdown · CCP-aligned
An executive read on the rating, anomalies the rubric can’t see, and the diligence questions to put to the developer, generated over the full project record. Available on Pro.
Upgrade to ProReads the project's design, monitoring and verification documents where available, then tests the additionality argument, baseline, and quantification against the methodology, with quotes. Available on Pro.
Upgrade to ProProject documents
- Project Design Document — Combined cycle natural gas based grid connected power plant at Jegurupadu, India (CDM 5257, registered version, 1066 KB)Download →pdd · hosted copy · 1 KB
- Project Design Document — Jegurupadu (validation-stage/public availability version, 708 KB)Download →pdd · hosted copy · 1 KB
- Validation Report — Bureau Veritas India Pvt. Ltd. (VVM 1.2, 3497 KB)Download →verification · hosted copy · 1 KB
- Monitoring Report — 26 Jul 2012 to 01 Oct 2016 (issued, 555 KB)Download →monitoring · hosted copy · 1 KB
- PDD Appendix 1 — Emission Reductions Calculation Spreadsheet (ER_GVK, 169 KB)Download →other · hosted copy · 1 KB
- PDD Appendix 2 — GVK 228 MW Gas Financials (1 Dec 2011, 231 KB)Download →other · hosted copy · 1 KB
- PDD Appendix 3 — GVK 250 MW Coal Financials (1 Dec 2011, 240 KB)Download →other · hosted copy · 1 KB
- PDD Appendix 4 — Responses to CDM Completeness Check Comments (198 KB)Download →other · hosted copy · 1 KB
- CDM Project 5257 Registry Page — Full project detail, issuance history, document indexDownload →other · hosted copy · 1 KB
- AM0029 ver. 3 — Baseline Methodology for Grid Connected Electricity Generation Plants using Natural GasDownload →methodology · hosted copy · 1 KB
- COMMUNICATIONS AGREEMENT.pdfOpen →other · source link
- VCS Issuance Representation signed.pdfOpen →other · source link
- V-2-I-01-L-0212-GVK_MR.pdfDownload →monitoring · hosted copy · 758 KB
- GVK PDD-v6 - clean mode CDM.pdfDownload →pdd · hosted copy · 1,067 KB
- Jegurupadu 228 MW NG - VCS PD.pdfDownload →pdd · hosted copy · 555 KB
- PPRR GVKIL.pdfOpen →other · source link
- Jegurupadu 228 MW NG - VCS FVR.pdfDownload →verification · hosted copy · 519 KB
- Val Report_GVK_v03_cdm.pdfDownload →verification · hosted copy · 3,497 KB
- Jegurupadu 228 MW NG - VCS Deed.pdfDownload →verification · hosted copy · 45 KB
- V-2-I-01-L-0212-GVK_FVeR.pdfDownload →verification · hosted copy · 836 KB
- V-2-I-01-L-0212-GVK_Deed.PDFDownload →verification · hosted copy · 97 KB
Primary documents located by the document review. Hosted copies are served from CarbonDecode; source links open the original registry or developer page.
Gathers satellite and Earth-observation evidence (Global Forest Watch forest-loss, MethaneSAT/IMEO, published analyses) for the project area and assesses reversal and emissions anomalies, with sources. Available on Pro.
Upgrade to ProScoring rationale · auditable trail
See exactly why each dimension scored as it did, every rule, adjustment, and data point behind the grade. The auditable trail buyers and assurance teams need. Available on Pro.
Upgrade to ProRelated projects
All Natural Gas Electricity Generation →- BBBZhangjiagang Nature Gas Power Generation ProjectChina
- BBBNatural Gas based grid connected power project at Peddapuram, A.P. by Gautami Power LimitedIndia
- BBBNanjing Jinling Grid Connected Natural Gas Combined Cycle Power Plant ProjectChina
- BBBChina Guangdong Shenzhen Qianwan LNG generation projectChina
- BBBGuangdong Huizhou LNG Power Generation ProjectChina
- BBBGrid connected electricity generation plant using natural gas at Jurong Island in SingaporeSingapore