Antai Group Waste Gas Recovery for Power Generation Project (300303)
Industrial & Commercial · Waste Gas Recovery · China
CORSIA-approved programmeDimension breakdown · CCP-aligned
An executive read on the rating, anomalies the rubric can’t see, and the diligence questions to put to the developer, generated over the full project record. Available on Pro.
Upgrade to ProReads the project's design, monitoring and verification documents where available, then tests the additionality argument, baseline, and quantification against the methodology, with quotes. Available on Pro.
Upgrade to ProProject documents
- GCC Portal Entry S00355 – Antai 1×40MW Waste Heat Utilization for Power Generation Project (Project Submission Form)Open →other · source link
- GCC Portal Entry S00355 – Antai IRR Calculation SheetOpen →other · source link
- ACM0012 Version 01 – Consolidated baseline methodology for GHG emission reductions from waste energy recovery projects (CDM EB32 Annex 8)Download →methodology · hosted copy · 0 KB
- Gold Standard Registry Project Page – GS ID 1154 (JavaScript-gated; no direct document URL retrievable)Download →other · hosted copy · 2 KB
- Monitoring Report_1st monitoring period_27-07-2008 to 31-12-2010_v2.pdf (Preliminary Review)Open →monitoring · source link
- Verification Report_3rd monitoring period_01-03-2012 to 28-02-2013_v1.1.pdf (Preliminary Review)Open →verification · source link
- Monitoring Report_2nd monitoring period_01-01-2011 to 29-02-2012_v1.3.pdf (Preliminary Review)Open →monitoring · source link
- GS Passport_20-05-10.pdf (Preliminary Review)Open →other · source link
- Verification Report_2nd monitoring period_01-01-2011 to 29-02-2012_v1.1.pdf (Preliminary Review)Open →verification · source link
- PDD_20-03-2013.doc (Preliminary Review)Open →pdd · source link
- Verification Report_1st monitoring period_27-07-2008 to 31-12-2010_v1.pdf (Preliminary Review)Open →verification · source link
- Monitoring Report_3rd monitoring period_01-03-2012 to 28-02-2013_v2.1.pdf (Preliminary Review)Open →monitoring · source link
- GS Validation Report 21.05.2010.pdf (Design Review)Open →verification · source link
- PDD 27.08.2008_v1.pdf (Design Review)Open →pdd · source link
- PDD 29.04.2009_v1.pdf (Design Review)Open →pdd · source link
- GS Passport Final.pdf (Design Review)Open →other · source link
- GS Passport 20.05.2010_v2.1.pdf (Design Review)Open →other · source link
- GS Passport July 2008_v2.pdf (Design Review)Open →other · source link
- PDD 28.04.2010_v2.3.pdf (Design Review)Open →pdd · source link
- (1)Monitoring Report_1st monitoring period_27-07-2008 to 31-12-2010_v2.pdf (Performance Review no. 1)Open →monitoring · source link
- (1)Verification Report_1st monitoring period_27-07-2008 to 31-12-2010_v1.pdf (Performance Review no. 1)Open →verification · source link
- (1)Verification Report_2nd monitoring period_01-01-2011 to 29-02-2012_v1.1.pdf (Performance Review no. 2)Open →verification · source link
- (1)Monitoring Report_2nd monitoring period_01-01-2011 to 29-02-2012_v1.3.pdf (Performance Review no. 2)Open →monitoring · source link
- (1)Monitoring Report_3rd monitoring period_01-03-2012 to 28-02-2013_v2.1.pdf (Performance Review no. 3)Open →monitoring · source link
- (1)Verification Report_3rd monitoring period_01-03-2012 to 28-02-2013_v1.1.pdf (Performance Review no. 3)Open →verification · source link
- Verification Report_4th monitoring period_26-12-2016 to 26-07-2018_v2.2.pdf (Performance Review no. 4)Open →verification · source link
- Antai MR-clean.pdf (Performance Review no. 4)Open →monitoring · source link
Primary documents located by the document review. Hosted copies are served from CarbonDecode; source links open the original registry or developer page.
Gathers satellite and Earth-observation evidence (Global Forest Watch forest-loss, MethaneSAT/IMEO, published analyses) for the project area and assesses reversal and emissions anomalies, with sources. Available on Pro.
Upgrade to ProScoring rationale · auditable trail
See exactly why each dimension scored as it did, every rule, adjustment, and data point behind the grade. The auditable trail buyers and assurance teams need. Available on Pro.
Upgrade to ProRelated projects
All Waste Gas Recovery →- BBBThe Hyundai Waste Energy Recovery CO-Generation Project Phase IISouth Korea
- BBBChuanwei Group 24 MW Waste Gas based Captive Power PlantChina
- BBBAssociated Gas Recovery and Utilization at Khamilah oil field area at Block-27 in Wilayat lbri of the Sultanate of OmanOman
- BBBMedcoEnergi Associated Gas Recovery and Utilization ProjectIndonesia
- BBBAssociated Gas Recovery and Utilization at Block 9Oman
- BBBNanba Associated Gas Processing Plant and the Auxiliary EngineeringChina